CAG Audit Uncovers Major Irregularities in Delhi CM's Official Residence Renovation
A recent audit by the Comptroller and Auditor General of India has exposed significant financial and procedural lapses in the renovation of former Delhi Chief Minister Arvind Kejriwal's official residence at 6, Flagstaff Road. The report, tabled in the Assembly, reveals that the project cost ballooned to over four times the original estimate, raising serious concerns about governance and accountability.
Staggering Cost Escalation and Scope Changes
The renovation work was initially awarded at Rs 8.6 crore but was ultimately completed at approximately Rs 33.6 to Rs 33.7 crore. This represents a staggering increase of nearly 300% from the original budget. The audit identified that a substantial portion of this escalation—nearly Rs 18.8 to Rs 18.9 crore—was spent on extra items that exceeded approved limits.
These additional expenditures included high-end specifications, artistic features, antique elements, and ornamental works that were not part of the original plan. Furthermore, the built-up area of the residence was expanded by 36%, growing from 1,397 square meters to 1,905 square meters. This significant change in project scope contributed substantially to the cost overruns.
Irregularities in Tendering and Contractor Selection
The CAG report raised multiple red flags regarding the tendering process. Restricted bidding was adopted at various stages without adequate justification, limiting competition and transparency. The selection of three consultancy firms lacked a clear recorded basis, and consultancy costs were inflated by 50% using outdated rate benchmarks.
Contractor selection also came under scrutiny. While five firms were initially shortlisted for the work, only one was found to meet the prescribed eligibility criteria. Despite this, substantial portions of the project—including works worth Rs 25.8 crore—were executed through the same contractor under revised estimates without inviting fresh bids. This approach effectively eliminated competitive pricing opportunities and raised questions about procurement fairness.
Fund Diversion and Incomplete Related Projects
The audit further highlighted financial and execution lapses in a related project involving the staff block and camp office. Although Rs 19.8 crore was sanctioned for this purpose, funds were diverted to other works. The staff block was never constructed, and servant quarters were instead built at a different location.
Meanwhile, the camp office was downgraded from a permanent to a semi-permanent structure and left incomplete after funds were exhausted. Only the basic structure was completed before the project was eventually foreclosed in June 2023. This represents a clear case of mismanagement and failure to deliver on planned infrastructure.
Procedural Lapses and Political Controversy
In another instance of procedural failure, a revised estimate of Rs 9.3 crore was approved more than two months after the work had already been completed. This created liabilities without prior sanction, violating established financial protocols.
The issue has already triggered political controversy, with the BJP branding the residence as "Sheesh Mahal" ahead of the 2025 Delhi Assembly elections. Reacting to the audit findings, the Aam Aadmi Party dismissed the report as politically motivated, stating that multiple probes over the past three years had failed to establish any wrongdoing and emphasizing that the property remains an official residence.
The CAG audit findings raise important questions about financial discipline, transparency in government projects, and adherence to established procedures in public works. As the political debate continues, the report serves as a critical document highlighting the need for greater accountability in the use of public funds for official infrastructure projects.



