Chennai's 413m Mega Curve Over Kathipara to Transform Metro Phase II
Chennai Metro's Dramatic Kathipara Curve Nears Completion

Chennai's skyline is set to witness an engineering marvel as the Metro Rail's Phase II project introduces its most dramatic feature yet - a sweeping 413-meter curved viaduct soaring above the bustling Kathipara junction. This architectural masterpiece promises to redefine daily commuting by blending cutting-edge engineering with breathtaking urban vistas.

Engineering Marvel Takes Shape

The upcoming alignment on Corridor 5 showcases a meticulously designed tight curve with a 125-meter radius, allowing trains to navigate smoothly above major road networks. What makes this segment particularly remarkable is how it maintains optimal balance and speed through a carefully engineered elevated pathway that seems to defy conventional transit design.

As trains approach Alandur station, they will execute a controlled descent from nearly 33 meters down to 27 meters, all while maintaining a steady speed of 35 kilometers per hour. This seamless vertical transition is made possible by an innovative balanced-cantilever structure specifically designed to handle such steep gradients without compromising passenger comfort or safety.

Construction Milestones and Methodology

The multi-span viaduct comprises five major spans, with the longest segment stretching an impressive 100 meters between two pillars. Construction teams have made significant progress, with the longest span nearly complete and showing steady advancement in the massive overhead system.

Currently, two projecting cantilever arms over Kathipara are approaching their crucial joining point. Workers are using advanced suspended shuttering methods to seal the minimal gap that remains, eliminating the need for ground-based platforms and demonstrating innovative construction techniques.

The assembly process involves installing ten precision-made segments on each cantilever arm using four specialized travelling form units. This meticulous approach ensures perfect alignment before tensioned steel strands permanently lock everything into position, creating a structurally sound and durable infrastructure.

Structural Integrity and Completion Timeline

Following the connection of the two cantilever arms, engineers initiate a critical second phase of cable stressing to enhance the structural strength. This process ensures the entire elevated curve remains secure under the dynamic forces generated by moving trains, guaranteeing long-term stability and safety for daily operations.

Metro officials have set a firm target of February completion for this dramatic curve, marking a significant milestone in the Phase II development. Once operational, this unique infrastructure element will not only improve connectivity but also provide passengers with unprecedented metropolitan views, transforming routine travel into an extraordinary experience.

The Kathipara curve represents more than just transit infrastructure - it symbolizes Chennai's growing prowess in urban development and engineering innovation. As construction progresses toward the February deadline, commuters can anticipate a revolutionary addition to the city's public transportation network that combines functional excellence with visual spectacle.