Mumbai's Goregaon Flyover Project Cost Triples, Civic Committee Demands Probe
Mumbai Goregaon Flyover Cost Triples, Civic Probe Ordered

Mumbai's Goregaon Flyover Project Faces Intense Scrutiny Over Soaring Costs

The escalating costs of the Mrunaltai Gore Flyover extension in Goregaon came under intense scrutiny during Wednesday's civic standing committee meeting. Members raised serious concerns as the project's budget has nearly tripled over the past seven years, prompting immediate action from municipal authorities.

Project Costs Skyrocket From Initial Estimates

The construction contract for extending the flyover along S V Road from Ram Mandir Road to Relief Road was originally approved at Rs 209.64 crore, inclusive of various taxes. However, the latest figures reveal a staggering escalation of Rs 38.33 crore, bringing the total project cost to Rs 247.97 crore. This substantial increase represents a dramatic budget overrun that has alarmed civic representatives across political affiliations.

The construction work is being executed through the joint venture company MEPL-GYAN JV, whose performance and cost management practices are now under the microscope. The proposal for final approval of these escalated costs was deferred following vigorous debate among committee members who highlighted multiple systemic failures.

Wide Pickt banner — collaborative shopping lists app for Telegram, phone mockup with grocery list

Cross-Party Concerns Over Delays and Planning Failures

Corporators from various political parties united in their criticism of the project's management. UBT Shiv Sena corporator Yashodhar Phanse, who initiated the call for a site visit, questioned the prolonged delay in completing the flyover extension, noting that the project has remained pending for over seven years without satisfactory progress.

BJP corporator Priti Satam raised fundamental questions about the initial planning process and the consultant's estimates. "How is it possible that such significant discrepancies only surfaced after four years of work?" she demanded during the committee proceedings. Satam went further to suggest the possibility of a concerning nexus between the project consultant and the contractor, calling for thorough investigation.

Accountability Demands and Financial Irregularities

Congress group leader Ashraf Azmi challenged the lack of accountability mechanisms, questioning why no penalties had been imposed on the contractor despite the extensive project delays. He specifically highlighted the allocation of nearly Rs 15 crore toward resurfacing work and noise barrier installation, asking why these substantial expenditures weren't identified and approved during earlier planning stages.

Leader of the House Ganesh Khankar insisted that both the project consultant and civic engineers must be present during the upcoming site inspection to provide detailed explanations for the cost escalation. This demand reflects growing frustration with what many committee members perceive as inadequate oversight and justification for the ballooning budget.

Immediate Action and Future Steps

Standing committee chairman Prabhakar Shinde announced that committee members will conduct a joint site visit to the Goregaon project location accompanied by municipal officials. This hands-on assessment aims to evaluate the actual ground situation and progress before any decision regarding the revised cost approval is made.

The committee's decisive action represents a significant shift toward greater accountability in Mumbai's infrastructure development. By deferring the cost approval and demanding physical verification, civic authorities are sending a clear message about the need for transparency and fiscal responsibility in public projects.

This development comes at a crucial time for Mumbai's infrastructure landscape, where timely completion and budget adherence are increasingly important for addressing the city's growing transportation needs. The outcome of the site inspection and subsequent committee decision will likely set important precedents for how future infrastructure projects are managed and monitored within the municipal framework.

Pickt after-article banner — collaborative shopping lists app with family illustration