Pune Airport's New Security Hold Area Nears Completion, Faces Regulatory Hurdles
Pune Airport SHA Nears Finish, Faces Delays to May Launch

Pune Airport's New Security Hold Area Progresses Amid Regulatory Scrutiny

The construction of the new Security Hold Area (SHA) at Pune Airport is advancing swiftly, with senior airport officials projecting completion by the end of March 2026. This development is part of a broader effort to enhance infrastructure at one of India's busiest aviation hubs.

Regulatory Approvals Required Before Operational Launch

Following construction, the Bureau of Civil Aviation Security (BCAS) must conduct a thorough inspection of the facility. Operations cannot commence until all regulatory approvals and compliance checks are successfully completed, a standard procedure for aviation security infrastructure.

Strategic Location in Old Arrival Section

The new SHA is being developed within the old arrival area of the airport, which has already been seamlessly integrated with the newer terminal building. This strategic use of existing space optimizes the airport's layout without requiring extensive new construction.

Expansion to Alleviate Congestion and Enhance Facilities

With the addition of the SHA, Pune Airport will gain significant extra departure space, directly addressing congestion issues. Passengers will benefit from more spacious waiting areas and improved amenities, contributing to a smoother travel experience.

Historical Context of Delays Due to Regulatory Changes

Officials have noted that past projects, including the new terminal building inaugurated in March 2024, faced similar delays. Full operational status was achieved only by July 2024 due to pending approvals and recommended modifications, highlighting the complex regulatory environment.

Steady Growth in Passenger Traffic

In 2025, Pune Airport recorded over 1.08 crore passenger movements, a notable increase from 1.02 crore in 2024. This steady growth underscores the mounting pressure on existing infrastructure and the urgent need for expansion.

Infrastructure Enhancements with the New SHA

The new SHA will add 4,000 square metres of space, significantly boosting capacity. It will also include:

  • 14 additional check-in counters
  • Three XBIS security screening machines
  • Two extra boarding gates

These upgrades are designed to streamline passenger flow and enhance security efficiency.

Anticipated Rise in Flight Movements

With an expected increase of 10 lakh additional passengers this year, flight movements are likely to rise correspondingly. The SHA is critical for managing this growth and ensuring smoother, more efficient operations.

Passenger Concerns Over Deadline Extensions

Flyers have expressed dissatisfaction with repeated deadline extensions, noting that earlier timelines for completion and regulatory clearance have not been met as promised. This has led to frustration among frequent travelers relying on improved facilities.

Commissioning Process to Extend Timeline

Even after physical construction is finished, commissioning procedures, detailed inspections, and regulatory clearances are expected to delay the operational launch. The likely start date is now projected to be around May 2026, pushing back initial expectations.

In summary, while the new SHA at Pune Airport represents a significant step forward in infrastructure development, its journey to becoming operational involves navigating a complex web of regulatory requirements. The project aims to address growing passenger demands but faces challenges in meeting tight deadlines amid necessary safety and compliance protocols.