Mumbai Metro Line 6 achieves major engineering feat over railway tracks
Mumbai Metro Line 6 achieves major engineering feat over tracks

MUMBAI: A significant engineering milestone was achieved on the under-construction Lokhandwala-Vikhroli Metro Line 6 in the days leading up to Sunday. Engineers and workers first constructed a critical pier along Western Railway tracks within an active train zone, followed by the launch of a 42-metre steel composite span over the tracks, marking one of the most challenging stretches between Ram Mandir and Jogeshwari stations.

Coordinated Operation

The launch was carried out by the Mumbai Metropolitan Region Development Authority (MMRDA) in coordination with Western Railway in the early hours of Sunday. The 14.5 km Pink Line is fully elevated, featuring 13 stations and a 15.2-hectare depot at Kanjurmarg.

An MMRDA official stated that the pier was built between the up-through and down-through railway lines in a highly confined, high-risk location. The foundation and pier construction were executed under stringent railway safety norms despite continuous train movement, limited night working windows, and intensive monitoring requirements.

Wide Pickt banner — collaborative shopping lists app for Telegram, phone mockup with grocery list

Night Block and Equipment

To facilitate the launch of steel girders, Western Railway implemented a major night block on its suburban section between Saturday and Sunday. WR chief spokesperson Vineet Abhishek said the block between Ram Mandir and Jogeshwari enabled the girder launch for Metro Line 6. The operation included a three-hour traffic and overhead equipment (OHE) block on the 6th line, along with a 10-hour block for crane stabling until Sunday morning.

The operation required meticulous planning and heavy machinery. Equipment deployed included a 600-ton crane, two 500-ton cranes, two additional standby cranes of similar capacity, two hydras, two JCBs, a material lifter, and two tower wagons. A total of 110 personnel were involved, including 40 railway staff and 70 contractor staff.

Simultaneous Block at Dahisar

Simultaneously, Western Railway carried out another major block at Dahisar to launch girders for two footoverbridges. This block affected the down slow, up slow, and down fast lines from 2:05 am to 4:05 am, while the up fast line remained blocked from 2:05 am to 3:05 am.

“With 88% of civil work completed on Metro Line 6, this milestone reflects precision, planning, and strong coordination with Western Railway,” an MMRDA official said.