Punjab RERA orders Rs 25 lakh delay interest to homebuyers from booking date
Punjab RERA orders Rs 25 lakh interest to homebuyers from booking date

In a significant ruling, the Punjab Real Estate Regulatory Authority (RERA) has directed a real estate promoter to pay approximately Rs 25 lakh as delay interest to homebuyers, holding that project timelines must be counted from the initial booking date rather than the execution of the sale agreement.

Case Background

The complainants, faculty members of Punjab Engineering College in Sector 12, had alleged facing delays in possession of their property. The case was argued by advocate M Shahnawaz Khan.

Key Findings

In a key finding, the authority held that where initial booking was made in 2018, the promoter could not defer liability by delaying execution of the agreement, which in this case was signed in December 2022 with a possession date of July 31, 2023.

Wide Pickt banner — collaborative shopping lists app for Telegram, phone mockup with grocery list

Relying on Supreme Court precedents, RERA ruled that the reasonable period for delivery of possession is capped at three years from the date of booking or advance payment, regardless of when the formal agreement is executed.

Compensation and Rejection of Builder's Plea

The authority quantified the delay interest payable to the complainants at approximately Rs 25 lakh as on the date of the order. It also rejected the builder's plea seeking extension on grounds of Covid-19, observing that force majeure provisions cannot be used as blanket protection where delays are attributable to the developer.

Counsel for the complainants said the order reinforces the principle that the rights of homebuyers flow from the date of booking and payment, and not merely from the execution of agreements.

Why It Matters

  • Who benefited: PEC faculty members (allottees)
  • Key ruling: Timeline counts from booking date, not sale agreement
  • Booking year: 2018 | Agreement signed: December 2022
  • Possession deadline cited: July 31, 2023

Legal Takeaway

  • Maximum reasonable delivery period is 3 years from booking/payment
  • Builders cannot defer liability by delaying agreements

Builder's Defence

The Covid-19 force majeure plea was rejected.

Impact

This ruling strengthens homebuyers' rights and sets a precedent against project delays and misuse of timelines.

Pickt after-article banner — collaborative shopping lists app with family illustration